ULURP Certification

In NYC practice, certification marks the start of the ULURP clock: DCP determines the application is complete and ready for formal public review and distributes it to reviewing bodies. NYC ULURP guidance notes that if environmental review is required, certain CEQR determinations or milestones (e.g., a negative declaration or a notice of completion for a draft EIS) must occur before certification.

Where it applies
New York City
When it comes up
Entitlements; ULURP initiation
Property types
All (NYC discretionary actions)

In practice

"Cert readiness" is a documentation discipline: incomplete submittals delay the only unbounded portion of ULURP (pre-cert), which is often the real schedule risk.

Related terms

CertificationCEQRNegative DeclarationDraft EISPre-certification Review